Whyalla renewable energy projects: wind turbines and solar panels across South Australia's Upper Spencer Gulf region

South Australia has selected four renewable energy developers to advance four Whyalla renewable energy projects with almost 13 gigawatts (GW) of combined wind and solar capacity in the Whyalla West release area, the state government announced on 18 October 2026. The selection — the first outcome from a land-release tender under South Australia’s Hydrogen and Renewable Energy Act 2023 — represents one of the largest renewable energy opportunities ever released in the state.

The four proposals, spread across more than 3,300 square kilometres of pastoral land west of the industrial centre of Whyalla in the Upper Spencer Gulf region, together represent roughly 12.65 GW of proposed wind and solar generation — the figure state officials are citing as “almost 13 GW”. To put that in perspective, South Australia currently has about 3 GW of grid-scale wind and solar installed, meaning the new proposals would more than quadruple the state’s existing capacity.

Four Whyalla renewable energy projects, four developers

Australian developer Windlab was awarded the largest slot: a proposed 6 GW wind-and-solar hybrid project across approximately 2,386 square kilometres. The project’s first stage is expected to comprise up to 1 GW of wind generation plus battery energy storage.

South Australia-based Altra Energy follows with a 4.7 GW wind-and-solar proposal across 584 square kilometres, while Heron Energy is pursuing a 1.6 GW wind project across 314 square kilometres. French developer Neoen, which already operates large-scale solar and battery storage assets elsewhere in South Australia, was selected for a considerably smaller solar project of around 350 MW across 81 square kilometres.

Whyalla renewable energy: wind turbine blades and solar panels at a South Australian wind-solar site
Wind and solar are set to transform the Whyalla region under South Australia’s land-release tender. (Image: Watan News)

What happens next — and what it is not

The selection gives each developer the exclusive right to apply for a renewable energy feasibility licence in the Whyalla West release area. It does not constitute construction approval or a final investment decision: investment amounts and commissioning schedules remain undisclosed, and each project must still pass feasibility studies and planning processes.

The Whyalla West area sits within Barngarla Country and is part of more than 11,000 square kilometres of land the South Australian government opened earlier this year for potential large-scale renewables development.

Why Whyalla matters for South Australia’s green future

South Australia’s Minister for Energy and Mining, Tom Koutsantonis, framed the announcement around the region’s industrial legacy. “For generations, Whyalla has been one of South Australia’s great industrial centres,” he said. “We want to build on that strength, attracting new investment and creating opportunities for the next generation of industry.”

“This is an extraordinary opportunity for Whyalla and the Upper Spencer Gulf, with almost 13 GW of proposed renewable energy generation that could help shape the region’s industrial future,” he added.

The state already sources a world-leading share of its electricity from renewables: its nearly 3 GW of grid-scale wind and solar, combined with more than 2 GW of rooftop solar, covers roughly 75 per cent of South Australia’s annual electricity needs. The state has set a goal of reaching 100 per cent “net” renewables by the end of 2027 — a target analysts say may arrive slightly late, but which the Whyalla proposals are designed to support well beyond.

Read more: Australia smashes renewable investment record with 5.36 GW of wind and solar

FAKTA: The Whyalla renewable energy tender

  • What: Four developers selected to advance almost 13 GW of wind and solar proposals in the Whyalla West release area.
  • Who: Windlab (6 GW wind+solar), Altra Energy (4.7 GW wind+solar), Heron Energy (1.6 GW wind), Neoen (~350 MW solar).
  • Where: More than 3,300 sq km of pastoral land on Barngarla Country, west of Whyalla, Upper Spencer Gulf, South Australia.
  • Status: Exclusive right to apply for feasibility licences — not construction approval; investment and timelines undisclosed.
  • Context: First tender outcome under South Australia’s Hydrogen and Renewable Energy Act 2023; announced 18 October 2026.

Frequently asked questions

Where is the Whyalla West release area?

It is a designated renewable energy zone west of Whyalla, an industrial port city on South Australia’s Upper Spencer Gulf. It covers more than 3,300 square kilometres of pastoral land within Barngarla Country and is part of over 11,000 square kilometres the state opened for large-scale renewables development earlier in 2026.

Who are the four selected developers?

Windlab (Australian, 6 GW wind-and-solar hybrid — the largest proposal), Altra Energy (South Australian, 4.7 GW wind-and-solar), Heron Energy (1.6 GW wind), and Neoen (French, around 350 MW of solar). Neoen already operates solar and battery storage projects elsewhere in South Australia.

Will these projects definitely be built?

Not yet. The selection only gives the developers the exclusive right to apply for renewable energy feasibility licences. Each project must still complete feasibility studies, licensing and planning processes before any construction decision, and investment amounts and schedules have not been disclosed.

What is the Hydrogen and Renewable Energy Act 2023?

It is South Australia’s legislative framework for releasing government land for renewable energy and hydrogen projects. The Whyalla West tender is the first competitive land-release process completed under the act.

Why is this important for Australia’s climate goals?

South Australia is already a global leader in renewables, meeting roughly 75 per cent of its annual electricity needs from wind and solar. The state aims for 100 per cent “net” renewables by the end of 2027. The almost 13 GW proposed at Whyalla could more than quadruple the state’s grid-scale capacity and anchor the next generation of green industry around Whyalla.

Leave a Reply

Your email address will not be published. Required fields are marked *

Author

usman2344913@gmail.com

Related Posts

Portugal housing protest camps: tent camp cleared in a Portuguese city square

Portuguese Police Clear Housing Protest Camps in Lisbon and Porto, Arresting 55

Portuguese police cleared tent camps set up by housing protesters in Lisbon and Porto before dawn on Tuesday, ending occupations that had...

Read out all
Livsstilsændringer klimaundersøgelse - bæredygtige hjemmevaner med genbrug og genanvendelige produkter

77% af briterne har ændret livsstil for at bekæmpe miljøproblemer, viser ny ONS-undersøgelse

Den nye livsstilsændringer klimaundersøgelse fra det britiske statistikkontor ONS viser, at 77% af de voksne har ændret livsstil for at bekæmpe miljøproblemer,...

Read out all
ماحولیاتی طرز زندگی سروے – پائیدار گھریلو عادات

ماحولیاتی طرز زندگی سروے: برطانیہ کے 77 فیصد بالغ ماحول کے لیے عادات بدل چکے ہیں

برطانیہ کے قومی شماریات کے ادارے او این ایس کے ماحولیاتی طرز زندگی سروے کے مطابق 77 فیصد بالغوں نے ماحولیاتی مسائل...

Read out all
UK climate lifestyle survey - sustainable home habits including recycling and reusable products

77% of Britons Changed Their Lifestyle to Tackle Environmental Issues, New ONS Survey Finds

The UK climate lifestyle survey from the ONS shows 77% of adults changed their lifestyle to tackle environmental issues while 85% felt...

Read out all
Riyadh airport flights — aircraft parked at King Khalid International Airport after reopening

Riyadh Airport Flight Disruptions Continue as Airlines Hold Off After Reopening

Riyadh airport flights remain heavily disrupted despite the reopening of King Khalid International Airport, with most of the world’s major airlines refusing...

Read out all
Iceni batterilager med rækker af battericontainere ved Hornsea 3's konverterstation

Ørsted færdiggør 600 MWh Iceni-batteri ved Hornsea 3 havvindmøllepark

Det danske energiselskab Ørsted meddelte den 20. oktober 2026, at byggeriet af selskabets Iceni batterilager ved Norwich i Norfolk i England er...